West Ealing Crossrail Complementary Measures consultation completed

03 April 2018

Ealing Council have completed the complementary measures consultation to the Manor Road area for when the new West Ealing station frontage is built.

West_Ealing_CCM_Consultation_plan_FINAL

The consultation report can be found on the council website.  As you will see, there was strong support for the proposals although turnout was low from residents.

The council will now proceed with detailed designs and plan to start construction later in 2018.  The later stages of construction will need to be fitted around Network Rail’s work on the station building scheduled to start in Summer 2018. Completion of both the station works and complementary measures is expected in late 2019.